Percentage of operation and maintenance activities of building in one year period
Repair of dining tables Proud Saet Thong Canteen
starts August 2023 and is completed October 2023
Renovation of Surerengchai volleyball court Surarengchai Student and Sports Activities Building
Contract starts June 2023 and is completed July 2023 Surarengchai Volleyball Court The Surarengchai Student Activities and Sports Building has been chosen as a training facility for female volleyball players. For the Asian Women's Volleyball Championship, The 22nd edition of 2023 will be held from 30 August - 6 September 2023.
Repair of student dormitory building group
start June 2023 Completion August 2023 Change the roof of Suraniwet 15 dormitory group to metal sheet
Road improvements The student dormitory area until Gate 4 Kalyanamit
starts November 2022 and is completed February 2023.
Renovation of the pedestrian walkway of the dormitory group to Gate 4 Kalyanamit
start June 2023 and be completed September 2023 Renovation of the pedestrian walkway of the dormitory group to Gate 4 Kalyanamit Contract start June 2023 and be completed September 2023
Renovation of student dormitory buildings damaged by rainstorms.
starts in June 2023 and is completed. August 2023 The thatch material of the Kaset Phiwat building has been replaced. Demolition of the ceiling of Suraniwet 13 dormitory service building and replacement of roof tiles.
Building renovation project to solve leakage problem 28 units
Starts in March 2023 and will be completed in July 2023.
Description:
***Renovation of buildings and grounds does not affect teaching and learning because it is done during
holidays and school holidays.
1 Total campus buildings area 756,482 m2
2 Total operated building 756,482 m2
Percentage building that operated and maintenanced 100%